Road works in Naples: a month of road works and closures
This March is a month intense on the streets of Naples, with a series of interventions scheduled to involve different areas of the city.
Works in Piazza Nicola Amore
Even the suggestive Piazza Nicola Amore will not be immune from road works.
From 20 to 27 March, the square will be closed to vehicular traffic at night to allow for the installation of mixed poles, lighting fixtures, power lines and transverse poles to support the contact line.
It will be a little inconvenient, but it will be worth it to improve the safety of the area.
Works in Via Reggia di Portici, Via Volta, Via Vespucci and Via Nuova Marina
The extraordinary maintenance of the deteriorated sections of the roads will be at the center of the works planned for via Reggia di Portici, via Volta, via Vespucci and via Nuova Marina.
The first phase, 15 from March to 24, provides preparatory work for the road resurfacing.
The second stage, from 27 March to 7 April, provides for the actual repaving, with no parking where present.
It won't be easy find a parking space in the area, but try to be patient because the final result will certainly be appreciable.
Works at Via Acton
Finally, the roadway of via Acton (sea side) will be closed from March 22nd to April 15th to allow for the development of the road surface.
Vehicular traffic will be diverted into the tram lane, with the possibility of crossing the area through two different construction site areas.